Six weeks to go
The countdown to Move-In Day has officially begun.
But first: TILING IS FINALLY DONE!!!
Also done, although not pictured (because I forgot to snap photos): drainage work. All trenches have been dug, piped, and recovered. Now we can get to the fun stuff.
Here, in their entirety, are the remaining items on the construction calendar:
Interior paining/remainder of exterior painting (resumes tomorrow!)
Hardscaping
Landscaping (irrigation + pretty plants)
Appliance installation (soaking tub and toilets are already on site; other appliances will start showing up this month)
All trades finish work & fixtures (basically all the subs come back to put the finishing touches on their original work, like plumbing and electrical fixtures)
Inspections
Final clean-up